Schedule
Time required for the
project launch after the PIN approval:
Time required for documentation preparation (PDD): 9 months
Time required for contracts preparation: 1 months
Time required to meet financial obligations: 1 months
Time required for replacement lanterns and ARCSOL introduction: 24 months
Time required for construction and installation: 6 months
Time required for complex commissioning on the average 2 months
Project commencement date 2011
Date of the issuing the first CER 2012
Technical lifespan of the Project 15 years
Credit line duration 20 fiscal years
Current status of the Project: Clean Development Mechanism (CDM) - the
investor, sources of financing and supplier are not defined now.